The Grange

About: ES Group is a leading firm of Property and Asset Consultants employing almost 300 staff in 10 offices across the UK.
Needs: Following the collapse of the site developer ES Group’s client wanted the infrastructure of the site to be completed. There was a requirement to meet obligations with the existing tenants and to make the remaining development land attractive for sale.

grange-1grange-2grange-3


Client: ES Group

Location: Romsey, Hampshire


The TRS Service

Our works included:

  • Sundry tree works,
  • Service diversion,
  • Construction of new tarmacadam surfaced car park and access road,
  • Tarmacadam overlay of existing access road,
  • Formation of retaining structure to support new car park,
  • Installation and extension of drainage system including interceptor,
  • Installation of new lighting,
  • Formation of new bin and cycle storage area,
  • Making good to existing temporary car park,
  • Alterations to kerbing,
  • Landscaping and seeding.
Download a pdf of this case study here


Why TRS?

TRS worked closely with the client to provide a ‘best value’ outcome:

  • During the tender and pre-construction stages we put together a ‘shopping list’ of potential project cost savings to assist our client in hitting budgetary and time targets.
  • We proposed approximately £55k of savings of which approximately £30k was taken up. We also devised a strategy with the engineer for minimising the spoil required to be removed form site, which would have added significant cost to the project.
  • The team acted collaboratively through the project and our relationships with the downstream supply chain also played a significant part in this process.
  • Our cost-saving approach continued through the construction period with further design and scope rationalisation saving a further £5k.