
A full refurbishment of a split two storey office and warehouse at the central Bristol business park.
TRS Construction Solutions Ltd were required to work very closely to the Project Manager to meet the target âlong stop datesâ required to secure an incoming tenancy. The work included:
The Client was wedded to a âlong stopâ date to ensure surety of an incoming tenancy. This condensed the proposed programme by 3 weeks. Working closely with the wider construction team, we facilitated joint meetings between the key supply chain to collaboratively plan the project sequence and programme and thus provide a collective approach to managing the project to the required dates.
During the process several âvalue engineeringâ and cost saving alternatives were proposed and the project ultimately was delivered ÂŁ28,000 under budget and 2 days early.

