About: Corporate Building Consultancy work mainly within the south west working in both the commercial and educational markets. CBC are specialists in designing, altering and surveying educational buildings and work with all kinds of schools to provide high quality facilities which are flexible and fit for today’s teaching environment.
Needs: The school needed extra teaching space and used the existing library. The need for a library and a new isolation room was still apparent.. Building single storey extension gave a new library and isolation room.


Client: Corporate Building Consultancy -Mark Brothwell


The TRS Service:

Our works included:TRS had to create an enclosed site compound to ensure the site was completely safe. Works were started during term time to be completed by the end of August. The works included:-
Removal of existing flat roof to create a floor
Create a frame to take windows and cladding
Install roof beams and ceiling
Install new flat roof with roof light and edge protection and install new rainwater goods
Install external wooden cladding
Fit new windows
Decoration works
Electrical works to include power data and lighting
Installation of air conditioning units
Carpentry to include small stair case and new doors
New carpets and floor finishes
Reinstate green area effected by the site compound.

Download a pdf of this case study here


Why TRS?

The ability to deliver complex projects in a short period of time Professional and experienced contract management to ensure the supply chain worked like clockwork.
Experienced site manager to ensure the programme was delivered in a safe and proper manner
A flexible approach to working to optimise time available during the school opening hours.
Working closely with other suppliers ensured works were completed on time and on budget